Problem Regarding to The Calculation of The Cost #34
-
|
Hello, |
Beta Was this translation helpful? Give feedback.
Replies: 3 comments 1 reply
-
|
Dear @Fantasydog05 can you please provide some supplements such as plots or data files? |
Beta Was this translation helpful? Give feedback.
-
|
@rpintodecastro @imeb can you help to answer the question it is not totally clear to me. |
Beta Was this translation helpful? Give feedback.
-
|
Dear @Fantasydog05 and @JBRDLR, |
Beta Was this translation helpful? Give feedback.




Dear @Fantasydog05 and @JBRDLR,
We have implemented an emergency stop as following under Performance Metrics subsystem. This would imply a safety on the battery usage. Competitors are invited to avoid reaching these extreme cases.
For the moment, this has not been yet included in our evaluations in the sense to penalize this scenario; but please keep in mind that if simulation is terminated due to this stopping enforcement, is not a valid solution. In future update of the repository, we might include this in the evaluation to penalize to a large number.
I hope I could address your doubt. If not, please let me know.
Best,
Iman