- Prepare BOM per room
- Setup boxes
- Setup vocto
- 09:00 camera and microphone pickup at budgetcam locations (Seb, Egb)
- 12:00 arrival
- arrival on site: 6 ppl (Mark, Vasil+ 4 .bg)
- arrival of flight cases (boxes and cabling)
- arrival of vocto boxes
- install vocto boxes
- 15:00 arrival of cameras and microphones
- load fresh batteries in the microphones
- camera configuration
- microphone configuration
- 16:00 per-room installation
- central monitoring & overview: Vasil(?), Mark
- parallel 2 people teams each for AW, H, K, U
- priority to Janson (Julien Detrooz?) and K1105 "Lafontaine"
- per-room equipment
- 1 presenter box
- 1 camera box
- 1 camera with power supply
- 1 tripod
- 1 hdmi cable (camera->box)
- 1 XLR cable (microphone->camera)
- 1 set of sennheiser transmitter+receiver, lapel microphone
- 2 3.5->6.4 jack converters
- 1 3.5->3.5 audio cable (presenter laptop->box)
- 2 VGA cables (laptop->presenter box, presenter box->beamer)
- (OPTIONAL) 1 HDMI->VGA converter
- (OPTIONAL) 1 HDMI cable for the converter
- testing
- return cameras to central storage
- 21:00 time-we-should-be-done-by
- 08:00 installing cameras, testing
- 2 people teams each for AW, H, K, U
- priority to Janson (Julien Detrooz?) and K1105 "Lafontaine"
- 09:10 Streaming start
- 13:30 start replacing batteries
- 18:30 END of the day
- Copying recordings from the boxes
- Moving cameras back to K
- Start of the day: 08:30
- Installing cameras, testing
- Priority to J
- Streaming start: 09:40
- 13:30 start replacing batteries
- 18:10 END of the day
- Copying recordings from the boxes
- Dismantling
- 21:00 time-we-should-be-done-by