Data

The ExpansionPlanningData() class storages standard data for the IDAES-GTEP model. Within, it includes a function to load data structure using the Prescient data loader.

def load_prescient(self, data_path, options_dict=None):

   self.data_type = "prescient"
   options_dict = {
       "data_path": data_path,
       "input_format": "rts-gmlc",
       "start_date": "01-01-2020",
       "num_days": 365,
       "sced_horizon": 1,
       "sced_frequency_minutes": 60,
       "ruc_horizon": 36,
   }

   prescient_options = PrescientConfig()
   prescient_options.set_value(options_dict)

All the data is stored within the ExpansionPlanningModel() class and used for the solution of the model. Table 1 shows a detailed description of the relevant parameters included.

Table 1: Data needed per component in the ExpansionPlanningModel() class
Grid Components Type Units Description
loads Parameter   Demand at each bus
lossRate Parameter   Loss rate for each transmission line
extensionMultiplier Parameter   Cost of life extension multiplier
minOperatingReserve Parameter   Minimum operating reserve
minSpinningReserve Parameter   Minimum spinning reserve
peakLoad Parameter MW Maximum level of power demand
reserveMargin Parameter MW Unused power determined as a fraction of peakLoad
weights Parameter dimensionless  
investmentFactor Parameter dimensionless  
deficitPenalty Parameter MW Generation deficits
Generator Components      
lifetimes Parameter   Lifetime of each generator
startupCost Parameter   Startup cost for each generator
capitalMultiplier Parameter   Multiplier for new generator investments
startFuel Parameter   Fuel required to be consumed for startup process
fuelCost Parameter USD Cost per unit of fuel at each generator
emissionsFactor Parameter dimensionless CO_{2} emission factor for each generator
generatorInvestmentCost Parameter   Cost of investment in each new generator
maxSpinningReserve Parameter   Maximum spinning reserve available for each generator
maxQuickstartReserve Parameter   Maximum quickstart reserve available for each generator
rampUpRates Parameter   Ramp up rates for each generator
rampDownRates Parameter   Ramp down rates for each generator
gensAtRegion Parameter   Matching for each generator to its respective region
fixedOperatingCost Parameter USD Operating costs for each generator
Thermal Specific      
thermalCapacity Parameter   Maximum output of each thermal generator
thermalMin Parameter   Minimum output of each thermal generator
spinningReserveFraction Parameter   Maximum fraction of maximum thermal generation output as spinning reserve
quickstartReserveFraction Parameter   Maximum fraction of maximum thermal generation output as quickstart reserve transmission line
Renewable Specific      
renewableCapacity Parameter MW Maximum capacity of each renewable generator
renewableCapacityValue Parameter dimensionless Fraction of renewableCapacity that can be counted towards planning reserve requirement
renewableQuota Parameter MW  
curtailmentCost Parameter USD/MW Cost of curtailed renewable energy
loadShedCost Parameter USD Cost of load shedding
Transmission Line Components      
transmissionCapacity Parameter   Long term thermal capacity of each transmission line
distance Parameter   Distance between terminal buses for each transmission line
Branch Components      
branchInvestmentCost Parameter USD Cost of investment in each new branch
branchInvestmentCost Parameter USD  
branchCapitalMultiplier Parameter    
branchExtensionMultiplier Parameter    
.. currentmodule:: gtep.gtep_data

.. automodule:: gtep
    :members:

.. automodule:: gtep.gtep_data
    :members: