Managing capacity for reviewing contributions
Reviewing InnerSource contributions takes time and effort. This should be reflected in capacity planning, especially for larger contributions. Expectations and available capacity should be transparent so that contributors understand when their contributions will be reviewed and released.
Large InnerSource contributions are causing delays to other work in the team and/or contributions are taking longer to be released than expected. Reviewing contributions may be significant invisible work, not tracked in a team's agile development process.
The BBC's connected TV application are built by a number of teams, each with different areas of responsibility. They work on each other's areas of the codebase via InnerSource on a regular basis.
The team responsible for the build process for the JavaScript bundles received a major pull request, changing how dependencies were bundled. This PR introduced a new build time dependency, a new structure to the deployed JavaScript bundles, and touched 503 files, with 6,699 lines of code added and 2,828 lines of code deleted. A contribution of this size required significant time to code review, test, and ensure the team understood the new tooling and structure introduced. Normally, InnerSource contributions would be reviewed ad-hoc, but the team estimated that this review process would take days rather than hours. Reviewing this PR would have delayed the team's other work, so the team raised this with the team lead, delivery manager, and product manager, to prioritize this work against other work. Time was set aside to review this contribution at future date.
This process was formalized in the team:
- Larger contributions have a ticket created on the team's backlog and included in prioritization discussion alongside other tickets. The contributor will be informed of the priority call and given an estimate as to when it will be reviewed and released.
- Smaller contributions can still be reviewed ad-hoc.
Maintainers of a successful InnerSource project are finding it difficult to review contributions, especially large contributions. They do not want to disrupt their team's other work, but also want to support contributions by reviewing/releasing them in a timely fashion.
- Contributors expect timely feedback on their contributions
- Maintaining team are expected to deliver other work alongside reviewing contributions
- Missing communication between contributors and maintainers on expectations/lead time for contributions to be reviewed/released
- Tension in prioritizing InnerSource contributions against other work
- Reviewing larger contributions is tracked in the team's ticketing system/bug tracker (e.g. Jira, GitHub issues)
- Maintaining team is given time to review larger contributions in team capacity planning
- Reviewing contributions is prioritized against other work (e.g. in sprint planning)
- Maintainers communicate their capacity for reviewing contributions, the priority of contributions, and an estimate of when a contribution will be reviewed/released
- Maintaining team has a service level objective (SLO) (e.g. 2 working days) for contributions receiving initial feedback
Maintaining team understands the overhead of reviewing large contributions and is given capacity to do so. Delivery and product managers are better able to plan, estimate, and track other work in the team by accounting for the time taken to review InnerSource contributions. Contributors understand when their contribution will be reviewed and released, and how long before the maintainers will provide initial feedback.