This document outlines the core formulas used to drive the Retail Project Dashboard.
1. Time Intelligence & Variance
Measure Name
Description
Formula Logic
Schedule Variance (SUM)
Calculates the day difference between Baseline and Actual/Today. Handles row-level iteration using SUMX.
Checks if Actual_Finish exists. If yes, compare to Baseline. If no, compare TodayInPKT to Baseline.
Total_Days_Delayed
The average delay across selected projects.
Average('Project_schedules'[Days_Delayed])
Schedule Variance Actual
Similar to above but uses AVERAGEX for specific summary table contexts.
AVERAGEX('Project_Summary', ... logic ...)
SelectedStatusDate
Captures the currently selected date context.
SELECTEDVALUE('DateTable'[Date])
Complete Formula: Schedule Variance (SUM)
Schedule Variance (SUM) =
SUMX(
'Project_schedules',
VAR ActualFinishDate = 'Project_schedules'[Actual_Finish]
VAR BaselineFinishDate = 'Project_schedules'[Baseline_Finish]
-- Today's date in Pakistan Standard Time (UTC+5)
VAR TodayInPKT = DATE(YEAR(UTCNOW() + TIME(5, 0, 0)), MONTH(UTCNOW() + TIME(5, 0, 0)), DAY(UTCNOW() + TIME(5, 0, 0)))
RETURN
IF(
-- If an Actual Finish date exists, calculate the variance at completion.
NOT ISBLANK(ActualFinishDate),
DATEDIFF(ActualFinishDate, BaselineFinishDate, DAY),
-- Otherwise, calculate the difference between today (in PKT) and the baseline.
DATEDIFF(TodayInPKT, BaselineFinishDate, DAY)
)
)
Complete Formula: Schedule Variance Actual
Schedule Variance Actual =
AVERAGEX(
'Project_Summary',
VAR ActualFinishDate = 'Project_Summary'[Actual_Finish]
VAR BaselineFinishDate = 'Project_Summary'[Baseline_Finish]
-- Create a variable for today's date in Pakistan Standard Time (UTC+5)
VAR TodayInPKT = DATE(YEAR(UTCNOW() + TIME(5, 0, 0)), MONTH(UTCNOW() + TIME(5, 0, 0)), DAY(UTCNOW() + TIME(5, 0, 0)))
RETURN
IF(
-- If an Actual Finish date exists, the task is complete, so the variance is 0.
NOT ISBLANK(ActualFinishDate),
DATEDIFF(ActualFinishDate, BaselineFinishDate, DAY),
-- Otherwise, calculate the difference between the correct 'today' and the baseline.
DATEDIFF(TodayInPKT, BaselineFinishDate, DAY)
)
)
2. Formatting & UX
Measure Name
Description
Formula Logic
RowHighlightColor
Returns a Hex code for background formatting.
IF(PhaseType = "Heading", "#D3D3D3", Blank())
FontColor
Returns a color name for text formatting.
IF(PhaseType = "Heading", "Black", Blank())
Complete Formula: RowHighlightColor
RowHighlightColor =
VAR _currentType = MAX('Project_schedules'[PhaseType])
RETURN
IF(_currentType = "Heading", "#D3D3D3", Blank()) -- Light gray for the heading row, blank otherwise
Complete Formula: FontColor
FontColor =
VAR _currentType = MAX('Project_schedules'[PhaseType])
RETURN
IF(
_currentType = "Heading",
"Black", -- Black font for heading rows
BLANK() -- Returns null for other rows, using the default table color
)