decision nodes sensitivity analysis #438

Description

@MathiasAlerini

Decision analysis can be performed on decision nodes. Copilot suggests 3 approaches which could be considered.

  • Option Removal Analysis
  • Decision Leverage Analysis
  • Decision Importance Ranking

Most people do not perform this analysis enough.

Question:

"How valuable is each decision opportunity?"

Examples:

  • Drill appraisal well?
  • Delay decision?
  • Expand facility?
  • Farm down?
  • Abandon?

Here we are no longer testing uncertainty.

We are testing the strategy space itself.


Option Removal Analysis

Remove one decision alternative and recompute MEU.

Example:

1 Base MEU:
2 500 M$

Remove:

1 Delay option

New MEU:

1 450 M$

Value of flexibility:

1 50 M$

Message

1 The delay option contributes 50 M$
2 of strategic value.

This is very different from uncertainty sensitivity.


Decision Leverage Analysis

Measure:

$$ MEU_{best}-MEU_{worst} $$

at a decision node.

Example:

1 D3: Facility concept
2 
3 Tieback 520
4 FPSO 500
5 Minimal 420

Decision leverage:

1 100 M$

Message

1 This decision is strategically important.

High leverage decisions deserve management attention.


Decision Importance Ranking

For each decision node compute:

$$ EV(\text{optimal}) - EV(\text{suboptimal}) $$

Ranking example:

Decision Impact
Development concept 120
Appraisal 70
Expansion 30
Monitoring 10

Message

1 Not all decisions matter equally.

This is often a very powerful executive insight.

Metadata

Metadata

Assignees

No one assigned

    Labels

    Type

    No type

    Projects

    No projects

    Milestone

    No milestone

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions