New simulation Code #32174
Replies: 3 comments
-
|
I think @joshuahansel has worked on something related recently I think multiple cycles might just mean a longer time history? With functions to describe the injection production profiles over multiple cycles? |
Beta Was this translation helpful? Give feedback.
-
|
Thanks for response. Can you kindly share the work because I couldn't find that. No multiple cycles means lets say if you inject gas and then produce after 6 months. This is one cycle. If you do 10 cycles with consecutive injections and production, multiple properties like gas recovery changes because of this. I am currently working on THM coupling for gas injection and production cycles at pore-scale (OpenPNM) and Reservoir-Scale (CMG-GEM). I wanted to do similar work using moose. Do you know on what similar topic i can do simulation which I can also publish on moose website. Thanks for your help. |
Beta Was this translation helpful? Give feedback.
-
|
I have been working on coupling THM and the porous flow module for geological hydrogen recovery. I use THM to make the 1D injection and production wells, and then I couple to 2D/3D porous flow in the fracture. I don't understand the points you are making about the multiple cycles. Like @GiudGiud , I thought you would do this by having a time-dependent inlet condition that does your various cycles. Are you saying this would be modeled some other way? |
Beta Was this translation helpful? Give feedback.
Uh oh!
There was an error while loading. Please reload this page.
-
Hi everyone,
I wanted to make new code for multiple injection-production cycles. I checked moose website and research papers that this work is not done previously. Can anyone confirm that this work has not been done previously?
Thanks.
Beta Was this translation helpful? Give feedback.
All reactions