05.01 — Latency Budgeting

Why this matters here: every other document in this tier is an answer. This one is the question. A latency budget is the single artifact that turns "make it faster" into a list of named, owned, measurable line items. Without it you will spend three weeks removing a 6.4 ns pipeline stage while a 30 m cross-connect quietly costs you 147 ns in each direction. The budget is how you find out which nanoseconds are worth having.


1. What a latency budget is

A latency budget is a table with one row per stage of the wire-to-wire path, where every row has:

Field Why it's mandatory
Stage A physical or logical block with a defined entry and exit event
Owner One named person. Not a team. Not "TBD".
Cycles At the stated clock (156.25 MHz → 6.4 ns/cycle)
ns (p50) Median contribution
Cumulative ns Running total — this is what makes overruns visible
Fixed / Variable Does this stage always take the same time?
Control Controllable / Physical / Uncontrollable (§4)

If a row is missing an owner, it is unowned latency and it will grow. If a row is missing a fixed/variable classification, you have not thought about jitter, and jitter is what actually loses the trade (§6).

The budget lives in docs/latency-budget.md and is updated in the same PR as any change that moves a number. A budget refreshed quarterly is decoration.


2. Choosing the measurement convention — do this first

Two systems quoting "400 ns tick-to-trade" can differ by 200 ns purely from convention. Pick one, write it at the top of the budget, and never quote a number without it.

Convention Definition Comment
First-bit-in → first-bit-out Start of inbound preamble at our tap → start of outbound preamble at the same tap Project default. Honest, includes serialization, comparable.
Last-bit-in → first-bit-out End of inbound frame → start of outbound frame Flatters you. Can be negative with speculative TX. Vendors love it.
Last-bit-in → last-bit-out Penalises you for your own frame size. Rare.
Fabric-only MAC RX SOF → MAC TX SOF Useful internally, never quote externally.

Project rule: all external numbers are first-bit-in → first-bit-out, measured at a single tap point with a single clock. Fabric-only numbers are always labelled "fabric".

Also fix the reference plane: are you measuring at your own SFP port, or at the venue's demarcation point in the meet-me room? The difference is your cross-connect — and it is usually the largest single line in the budget (§8).


3. The worked budget for this system

Baseline: 10GbE (0.8 ns/byte at the MAC layer), core clock 156.25 MHz (6.4 ns/cycle), Nasdaq TotalView-ITCH 5.0 in over MoldUDP64, OUCH 5.0 out, UltraScale+ with the fast path in one SLR. Trigger message: an ITCH Add Order that improves the inside.

Reference plane: the venue demarc, 30 m of single-mode fibre each way.

# Stage Owner Cyc ns Cum ns Fix/Var Control
P1 Cross-connect fibre, venue → us (30 m @ 4.9 ns/m) Infra 147.0 147.0 Fixed Physical
P2 SFP+ optical RX (ROSA + limiting amp) Infra 8.0 155.0 Fixed Uncontrollable
S1 Serialization: preamble+SFD+Eth+IP+UDP+Mold hdr (70 B) 56.0 211.0 Fixed Uncontrollable
S2 Serialization: ITCH body to last needed field (~30 B) Feed 24.0 235.0 Var (msg type) Semi
R1 GT RX PMA — CDR, deserialize, RX buffer bypassed IO 35.0 270.0 Fixed Controllable
R2 PCS RX — block sync, gearbox, descramble, 64b/66b IO 25.0 295.0 Fixed Controllable
R3 MAC RX — cut-through, preamble strip, no FCS wait IO 2 12.8 307.8 Fixed Controllable
R4 A/B feed arbitration + sequence check Feed 2 12.8 320.6 Var Controllable
R5 Deframe — MoldUDP64 strip, message split Feed 1 6.4 327.0 Var (msg N in pkt) Controllable
R6 Decode — type demux, field extract Feed 1 6.4 333.4 Fixed Controllable
R7 Symbol lookup — stock locate → book slot (BRAM + outreg) Book 2 12.8 346.2 Fixed Controllable
R8 Book update + top-of-book maintain Book 2 12.8 359.0 Var (bank collision) Controllable
R9 Strategy trigger evaluation Strat 1 6.4 365.4 Fixed Controllable
R10 Pre-trade risk gate Risk 2 12.8 378.2 Fixed Mandatory — do not remove
R11 Order encode — template read + field splice Gwy 2 12.8 391.0 Fixed Controllable
T1 MAC TX — SOF to first bit at PCS IO 2 12.8 403.8 Var (TX busy) Controllable
T2 PCS TX — scramble, 64b/66b encode, gearbox IO 20.0 423.8 Fixed Controllable
T3 GT TX PMA — serialize, TX buffer bypassed IO 30.0 453.8 Fixed Controllable
P3 SFP+ optical TX (driver + TOSA) Infra 8.0 461.8 Fixed Uncontrollable
P4 Cross-connect fibre, us → venue (30 m) Infra 147.0 608.8 Fixed Physical

Subtotals — read these, not the total:

Group Rows ns % of budget
Fibre + optics (physical) P1–P4 310.0 50.9 %
Serialization (uncontrollable) S1–S2 80.0 13.1 %
SerDes + PCS (IO stack, both ways) R1, R2, T2, T3 110.0 18.1 %
Our fabric (MAC RX → MAC TX) R3–T1 108.8 17.9 %

Verify: the GT PMA and PCS figures (R1, R2, T2, T3) are estimates for UltraScale+ GTY in a low-latency 10GBASE-R configuration with TX/RX buffers bypassed. Compute the exact latency for your configuration from the latency tables in UG578 (UltraScale Architecture GTY Transceivers) / UG576 (GTH), and the PCS/MAC figures from your Ethernet IP product guide (e.g. PG210, 10G/25G High Speed Ethernet Subsystem) — then measure on your hardware. Fibre propagation at 4.9 ns/m assumes a group index of ~1.468; confirm against your fibre datasheet.

The lesson from the subtotal table: you own 17.9 % of the number. Half the budget is glass. That does not make the fabric work pointless — 108.8 ns of fabric versus a competitor's 300 ns is the whole game — but it does mean the fibre line must be attacked with the same rigour as the decode pipeline, by the same team, in the same table.


4. Controllable vs uncontrollable lines

The discipline that saves the most engineering time is refusing to attack lines you cannot move.

Class Definition Examples here Correct response
Uncontrollable Physics or protocol. No engineering changes it. Serialization of the bytes you must receive (S1); speed of light in fibre; optical PMD delay Record it, subtract it, stop thinking about it
Physical Not logic, but a decision someone can make Cross-connect length, cable type, switch hops, rack position Escalate to whoever owns procurement/colo. Usually the cheapest ns in the building.
Semi-controllable Fixed given a choice you already made S2 — you must wait for the field you trigger on, but which field is a design choice Re-open the design choice
Controllable Your RTL, your IP config, your floorplan R3–T1, GT config This is where optimization work goes
Mandatory Controllable but off-limits R10 pre-trade risk, gap detection, drop counters Do not touch. See 05-optimization-playbook.md §8.

Three sharp consequences:

  1. You cannot beat serialization. If your trigger depends on a field 60 bytes into the frame, you wait 48 ns for it. The only lever is depending on an earlier field — which is a strategy decision, not an RTL one.
  2. You cannot beat the speed of light in glass. 4.9 ns/m is not negotiable. The number of metres is.
  3. You absolutely can beat your own decode pipeline, and it is the only part of the budget that responds to RTL work. Spend your engineering there and your political capital on the physical lines.

⚠️ A budget that lists only controllable lines looks great and is useless. It hides the fact that your 108 ns of fabric sits inside a 609 ns reality, and it lets a physical decision (a 60 m cross-connect) be made by someone who never sees the table.


5. Fixed vs variable, and where the variance comes from

Every Var row in §3 is a jitter source with a named cause. Name it or you cannot bound it.

Row Variance source Typical excursion (estimate)
S2 Message type and length differ; trigger field position varies 0–40 ns
R4 A vs B feed arrival skew; which line wins 0 to the A/B skew (µs-scale worst case)
R5 Your message is the Nth in a MoldUDP64 packet — you decode N−1 first 0 to (N−1) × decode cost
R8 Book bank collision → 1-cycle stall 0–6.4 ns
T1 TX busy with another frame — you wait for it to finish 0 to (frame bytes × 0.8 ns) + 16 ns

The T1 and R5 rows are the two that ruin real systems:

  • R5 (packet packing). MoldUDP64 packs multiple ITCH messages into one UDP datagram. If your Add Order is message 7 of 9, a serial decoder pays for six irrelevant messages first. Mitigations: decode multiple messages per beat, or dispatch by type in parallel across the packet. Budget the worst realistic N, not N=1.
  • T1 (TX occupancy). A 1500-byte frame in flight costs 1200 ns. If a heartbeat or a slow-path DMA-injected frame is transmitting when you decide to trade, you lose more than your entire fabric budget. Rule: nothing large ever shares the order-path MAC, and low-priority frames are pre-empted or scheduled into known quiet windows. Count every deferral.

⚠️ A "fixed-latency design" with an unbounded TX-occupancy line is not fixed-latency. Deterministic fabric plus a shared transmitter equals nondeterministic system.


6. Budget for jitter, not just the mean

The mean is the least useful statistic in this project. Every budget row carries four numbers, not one:

Stage p50 p99 p99.9 max N Load
R4 arbitration 12.8 12.8 19.2 25.6 4.1e6 open replay
R5 deframe 6.4 25.6 51.2 89.6 4.1e6 open replay
R8 book 12.8 12.8 19.2 19.2 4.1e6 open replay
T1 MAC TX 12.8 12.8 12.8 76.8 4.1e6 open replay
Wire-to-wire 608.8 628.0 672.0 736.0 4.1e6 open replay

Rules for this table:

  1. Percentiles do not add. The p99 of the total is not the sum of per-stage p99s — that sum is an upper bound, usually a loose one. Measure the total end-to-end and use per-stage percentiles only for attribution.
  2. Max is a real number, not an outlier to discard. In trading, the max is a trade you lost or a risk check you delayed. Report it. If you truncate the distribution, say exactly what you truncated and why.
  3. Always state N and the load condition. A p99.9 over N=1000 is noise. See 04-measurement-and-profiling.md §9.
  4. A design with lower p50 and worse p99.9 is a regression, unless someone argues otherwise in writing. Project default: determinism ≥ mean speed.

7. Budget debt

Blocks overrun. The failure mode is not the overrun — it's the silence.

Budget debt: when a stage exceeds its allocation, the excess is a debt. It must be repaid from another stage's slack, or the target moves. There is no third option, and "we'll get it back later" is not a plan, it is the debt.

Keep a ledger next to the budget:

Date Stage Allocated Actual Debt (ns) Repayment plan Owner Status
2026-06-14 R8 book update 1 cyc / 6.4 2 cyc / 12.8 +6.4 Merge R7 outreg into R8 addressing Book Open
2026-06-21 R11 encode 3 cyc / 19.2 2 cyc / 12.8 −6.4 Credit — offsets R8 Gwy Closed
2026-07-02 T1 MAC TX 1 cyc / 6.4 2 cyc / 12.8 +6.4 None. Target moved 600 → 609 ns. IO Accepted

Practices that make this work:

  • Debt is reviewed weekly, in public. Unreviewed debt compounds: two teams each quietly take one cycle and the target slips 12.8 ns with nobody responsible.
  • Credits are real. A block that comes in under budget banks slack. This is the only incentive that makes people optimize blocks that already "meet" budget.
  • Debt older than one sprint gets converted: either someone repays it, or the published target changes and everyone is told. Never carry silent debt into a release.
  • Design new blocks with reserve. If a block is allocated 12 cycles, build it in 9. Timing closure will consume the difference (see 00-foundations/05-timing-closure.md §7).

8. Physical lines belong in the same table

The most common structural mistake is keeping a "latency budget" for RTL and a separate spreadsheet for the data centre. They are one table.

Physical decision Latency effect Estimate Who decides today?
Cross-connect length (each way) 4.9 ns/m fibre; ~4.3 ns/m twinax copper 30 m → 147 ns Colo/infra
Cage position relative to the meet-me room Sets the above 10–100+ m Contract negotiation
One extra store-and-forward switch hop Frame must be fully received 64 B frame → ≥ 51 ns + switch Network
One extra cut-through switch hop Fixed per-hop ~300–500 ns (typical ToR class) Network
One extra layer-1 / low-latency hop Fixed per-hop ~4–130 ns depending on class Network
Optics vs passive DAC at short reach Skips the optical PMD ~5–15 ns/end Infra
Direct venue feed vs consolidated/SIP feed Feed pipeline delay 10²–10⁵ µs (dominates everything) Market data

Verify: switch and layer-1 device latencies vary by an order of magnitude across product classes. Take them from the vendor's published port-to-port figures for your exact model and frame size, then measure on your hardware with the tap method in 04-measurement-and-profiling.md.

The point of putting these in the same table is that the numbers become comparable. "Remove a switch hop: −400 ns, cost = one change request" sits directly above "merge two pipeline stages: −6.4 ns, cost = two weeks and a new class of bug", and the ordering becomes obvious to everyone, including people who do not write RTL.


9. Allocating a budget to a block that doesn't exist yet

You must give a number before the RTL is written, or the RTL will define the number. Procedure:

  1. Find the remaining slack. target − sum(committed rows). If it's negative, stop and renegotiate before writing code.

  2. Estimate from the shape of the work, in cycles:

    Work shape Cycles (estimate)
    Field extract / mux from a registered beat 1
    Comparison chain ≤ 8 wide 1
    BRAM read 1 + 1 (output register)
    URAM read 1 + 1, +1 per cascade hop
    Arbitration between N sources 1, +1 if it needs a skid buffer
    Read-modify-write with same-address forwarding 2
    Wide reduction (max over 32+ entries) 2–3, or 1 if maintained incrementally
    27×18 DSP multiply, registered 3–4
  3. Add one cycle of closure reserve per 3–4 cycles of logic. Declare it as reserve in the budget, not as work.

  4. Write the allocation into the module header before the first always_ff:

    // ─────────────────────────────────────────────────────────────
    //  Module      : book_update
    //  Owner       : <name>
    //  Latency     : 2 cycles (12.8 ns @ 156.25 MHz), FIXED
    //  Reserve     : 0 cycles  (spent at 2026-06-14, see debt ledger)
    //  Jitter      : +1 cycle on bank collision; counted in stall_cnt_o
    //  Budget row  : R8
    //  II          : 1 (must accept a beat every cycle)
    // ─────────────────────────────────────────────────────────────
  5. A block without a header budget is not reviewable. This is a hard rule in CLAUDE.md §4.


10. Regression gating: defending the budget in CI

A budget that is not enforced by a machine will be eroded by humans who each had a good reason.

What to gate on:

Gate Mechanism Failure action
Fabric cycle count cocotb test replays a golden pcap, asserts exact ingress→egress cycle delta per message class Fail the PR
Cycle count distribution Same test, asserts p99.9 and max cycle deltas Fail the PR
Post-route WNS/TNS Parse report_timing_summary Fail if WNS < 0, warn if WNS drops > 0.1 ns
Stage-level counts Per-stage counters read at end of sim, compared to latency-budget.json Fail on any increase

The PR rule: a change that adds a cycle to any fast-path stage must state, in the PR description, (a) which stage, (b) how many ns, (c) which row of the debt ledger absorbs it, and (d) why the alternative (precompute, widen, restructure) was rejected. Reviewers reject on a missing (d) more often than a missing (a).

Emit the machine-readable artifact from the testbench so the gate has something to diff:

{ "clock_mhz": 156.25,
  "stages": { "R3": 2, "R4": 2, "R5": 1, "R6": 1, "R7": 2,
              "R8": 2, "R9": 1, "R10": 2, "R11": 2, "T1": 2 },
  "fabric_cycles_p50": 17, "fabric_cycles_p999": 21, "fabric_cycles_max": 24,
  "n": 4132880, "source": "simulated", "trace": "itch_20260602_open.pcap" }

⚠️ Simulated cycle counts are not measured latency. A CI gate on simulated cycles catches architectural regressions only. It will not catch a GT reconfiguration, a floorplan change that adds route delay, or a MAC IP upgrade. Those need the hardware loop in 04-measurement-and-profiling.md.


11. Template — copy this for a new block

### Budget row: <ID> — <block name>

| Field | Value |
| --- | --- |
| Owner | <one name> |
| Entry event | <signal / condition that starts the clock> |
| Exit event | <signal / condition that stops it> |
| Allocated | <N> cycles / <N × 6.4> ns |
| Reserve included | <N> cycles |
| Fixed or variable | Fixed \| Variable (cause: ______) |
| Control class | Controllable \| Physical \| Uncontrollable \| Mandatory |
| Jitter bound | +<N> cycles worst case, counted in `<counter_name>` |
| II | 1 |
| Measured p50 / p99 / p99.9 / max | — / — / — / — (N=, load=) |
| Source of measurement | simulated \| measured |
| Debt | <ns, or "none"> |
| Repayment plan | <text, or "n/a"> |

12. Rules for this project

  1. One owner per row. No shared ownership, no "TBD".
  2. First-bit-in → first-bit-out, at one tap, with one clock, or it isn't a quotable number.
  3. Physical lines live in the same table as RTL lines.
  4. Four numbers per row (p50/p99/p99.9/max), plus N and load.
  5. Every overrun becomes a ledger entry the same day.
  6. Every new block gets an allocation before it gets a file.
  7. Attack controllable lines only — until the physical lines are demonstrably optimal, in which case escalate them, don't ignore them.
  8. The risk gate is a budget row like any other, and it is never the answer to a debt. See CLAUDE.md §5.