Close date set as the migration time #1376
Replies: 2 comments 18 replies
-
If the Source ClosedDate is empty then the Target Closed Date would be the date of the migration. Can you check to see if the Source data is in-tact? |
Beta Was this translation helpful? Give feedback.
-
My Agile Boards teams are also reporting this behavior. We see this on some migrated work items, but not all.
version 14.2.2 |
Beta Was this translation helpful? Give feedback.
-
Describe your issue:
A lot of WI has been migrated with the close time set as the migration data time, most of them Task type.
I would like to know if there is already a solution for this problem, either in the configuration, or if it is something that is being corrected for other versions.
migration time 30/01/2023
version. 12.0.36
Beta Was this translation helpful? Give feedback.