I have two ADO projects in a same org, but few of the Backlog items are already migrated to destination project, now we have a requirement of migrating all the existing items which are in below states "Closed, Removed, Done, Released & Design" and the Area and Iteration maps need to be same as Destination it should not overwrite with source things and It should ignore if the work item is already present in the destination. What is the query or the sample configuration file that i need to use to accomplish it. |
Beta Was this translation helpful? Give feedback.
Replies: 2 comments
-
@MrHinsh requesting your help to achieve this process |
Beta Was this translation helpful? Give feedback.
-
This is by default. If the tool detects an existing ReflectedWorkItemId it will not overwrite it. |
Beta Was this translation helpful? Give feedback.
This is by default.
If the tool detects an existing ReflectedWorkItemId it will not overwrite it.