Show task only if previous ones were completed #1379
-
You don't need to see task about "throwing trash out" if you haven't completed "taking it out of the bin". That's the essence of the goal I had in mind, basically. Possible solution |
Beta Was this translation helpful? Give feedback.
Replies: 2 comments 1 reply
-
Hi, sorry this is not possible in Tasks currently. Tasks sees these 2 successive lines as separate, independent tasks. There are multiple feature requests asking for the ability to create dependencies between tasks, but this is not currently possible. |
Beta Was this translation helpful? Give feedback.
-
It's also tricky due the way that recurrent tasks are working. If you have two recurrent tasks in the same file, the second one would never appear for example. |
Beta Was this translation helpful? Give feedback.
Hi, sorry this is not possible in Tasks currently.
Tasks sees these 2 successive lines as separate, independent tasks.
Tasks stores each task line as an independent object, with no links or relationships between them.
There are multiple feature requests asking for the ability to create dependencies between tasks, but this is not currently possible.