Sprint Planning Prep

Generate a sprint planning package: carryover report, velocity trend, per-member capacity, ready-for-planning queue, and sprint fill suggestions. Run before each bi-weekly sprint planning call.

Uses GraphQL for bulk reads (skip acli). Writes follow the API preference order in SKILL.md.

Authentication setup: see references/auth.md. All examples below assume AUTH, CLOUD_ID, and GRAPHQL_URL are set per that file.

Input

The caller provides:

  1. Team ID — Jira team UUID. If not provided, ask the user.
  2. Board ID — optional. If not provided, discover from references/jql-patterns.md board table or ask.
  3. Sprint — optional. Defaults to "plan the next sprint" (uses active sprint for carryover, next sprint as target).

Workflow

Step 1 — Resolve Sprint Context

Find the team's board and identify sprints. Use acli for sprint lookup (simple, single call):

acli jira board list-sprints --board BOARD_ID --state active --json
acli jira board list-sprints --board BOARD_ID --state closed --json --recent 3
acli jira board list-sprints --board BOARD_ID --state future --json --recent 1

Identify:

  • Active sprint (ending soon) — source for carryover
  • Next sprint (future) — target for planning
  • Last 3 closed sprints — source for velocity

Step 2 — Carryover Report

Issues in the active sprint that are NOT Closed or Release Pending. These carry into the next sprint.

curl -s -u "$AUTH" "$GRAPHQL_URL" -X POST \
  -H 'Content-Type: application/json' \
  -H 'X-ExperimentalApi: JiraIssueSearch' \
  -d '{
    "query": "query Carryover { jira { issueSearchStable(cloudId: \"'"$CLOUD_ID"'\", issueSearchInput: {jql: \"project in (RHIDP, RHDHPLAN, RHDHSUPP, RHDHBUGS) AND sprint = SPRINT_ID AND status not in (Closed, \\\"Release Pending\\\") AND \\\"Team[Team]\\\" = TEAM_ID\"}, first: 50) { totalCount edges { node { key summary status { name } assignee { name } storyPoints issueType { name } } } } } }"
  }'

Validation: Flag any Epics in the sprint — only Bug, Task, or Story should be in sprints. "⚠ RHIDP-1234 is an Epic — Epics should be broken down into Stories/Tasks, not added to sprints."

Sum carryover SP. If carryover > avg velocity, flag: "Carryover ({N} SP) exceeds avg velocity ({M} SP) — sprint is overcommitted before adding new work."

Step 3 — Velocity Calculation

For each of the last 3 closed sprints, count completed SP:

curl -s -u "$AUTH" "$GRAPHQL_URL" -X POST \
  -H 'Content-Type: application/json' \
  -H 'X-ExperimentalApi: JiraIssueSearch' \
  -d '{
    "query": "query Velocity { jira { issueSearchStable(cloudId: \"'"$CLOUD_ID"'\", issueSearchInput: {jql: \"project in (RHIDP, RHDHPLAN, RHDHSUPP, RHDHBUGS) AND sprint = SPRINT_ID AND status in (Closed, \\\"Release Pending\\\") AND \\\"Team[Team]\\\" = TEAM_ID\"}, first: 100) { totalCount edges { node { storyPoints } } } } }"
  }'

Compute: SP per sprint, 3-sprint average, trend (↑ accelerating / → stable / ↓ decelerating).

Step 4 — Per-Member Capacity

Reuse the capacity query from references/assign.md Layer 3. For each team member (roster from assign.md Layer 1):

  • Open issues in active sprint (carryover per person)
  • SP committed in active sprint
  • Issues in next sprint (already planned)
  • Overloaded flag (≥10 open issues or ≥21 SP)

Step 5 — Ready-for-Planning Queue

Backlog issues that are refined and ready to pull into the sprint:

jql: "project in (RHIDP, RHDHPLAN, RHDHSUPP, RHDHBUGS)
  AND \"Team[Team]\" = TEAM_ID
  AND status in (Backlog, \"To Do\")
  AND sprint not in (openSprints(), futureSprints())
  AND (cf[10028] is not EMPTY OR issuetype = Bug)
  AND issuetype in (Bug, Task, Story)
  ORDER BY priority ASC, created ASC"

Rank by priority, then by parent epic priority. Include: key, summary, priority, SP, parent epic key, assignee (if set).

Step 6 — Available Capacity

available_SP = avg_velocity - carryover_SP

If negative, warn: "No room for new work — carryover alone exceeds velocity."

Step 7 — Sprint Fill Suggestions

Automatically generate issue-to-person recommendations from the ready queue. Uses expertise matching from references/assign.md Layer 2 (if not already fetched, run it now).

For each ready-for-planning issue, score against each team member using the same formula from assign.md (expertise × 3 + proximity × 2 - capacity × 1). Suggest assignments up to available_SP.

Framing: "These are suggestions — team members self-select during planning."

Step 8 — Critical Customer Bugs

Separately surface any critical/blocker bugs with rhdh-customer label:

jql: "project in (RHIDP, RHDHBUGS) AND priority in (Blocker, Critical) AND labels = rhdh-customer AND \"Team[Team]\" = TEAM_ID AND status != Closed"

Note: "Critical customer bugs are exempt from capacity constraints — work immediately regardless of sprint load."

Step 9 — Continuous Improvement Items

Surface open issues with Component: Continuous Improvement (retro action items):

jql: "project = RHIDP AND component = 'Continuous Improvement' AND \"Team[Team]\" = TEAM_ID AND status != Closed ORDER BY priority ASC"

Note: "Retro action items to consider for this sprint."

Output

Data Contract

{
  "team": "RHDH Cope",
  "active_sprint": "Sprint 47",
  "target_sprint": "Sprint 48",
  "carryover": {
    "count": 5,
    "sp": 13,
    "items": [{"key": "...", "summary": "...", "assignee": "...", "status": "...", "sp": 5}],
    "epic_violations": ["RHIDP-1234"]
  },
  "velocity": {
    "sprints": [{"name": "Sprint 46", "sp": 21}, {"name": "Sprint 45", "sp": 18}],
    "average": 18,
    "trend": "accelerating"
  },
  "capacity": [
    {"name": "Allison Hill", "carryover_items": 2, "carryover_sp": 8, "open": 5, "sp_load": 13, "overloaded": false}
  ],
  "available_sp": 5,
  "ready_queue": [
    {"key": "...", "summary": "...", "priority": "Critical", "sp": 3, "parent_epic": "RHIDP-100"}
  ],
  "fill_suggestions": [
    {"key": "RHIDP-5678", "proposed_assignee": "Noah Rhodes", "score": 12, "rationale": "..."}
  ],
  "critical_customer_bugs": [],
  "ci_items": []
}

Markdown Template

## Sprint Planning — {team}

{active_sprint} → Planning {target_sprint}

### Carryover ({count} items, {sp} SP)
| # | Issue | Summary | Assignee | Status | SP | Days |
|---|-------|---------|----------|--------|----|------|

⚠ Carryover ({sp} SP) vs avg velocity ({avg} SP): {assessment}

### Velocity (last 3 sprints)
| Sprint | Completed SP | Trend |
|--------|-------------|-------|
Avg: {avg} SP | Trend: {trend}

### Capacity
| Member | Carryover | Open | SP Load | Status |
|--------|-----------|------|---------|--------|

### Available Capacity
Avg velocity: {avg} SP − Carryover: {carry_sp} SP = **{available} SP available**

### Ready for Planning ({count} items, {total_sp} SP in queue)
| # | Issue | P | Summary | SP | Parent Epic |
|---|-------|---|---------|----|----||

### Sprint Fill Suggestions
| # | Issue | Summary | Suggested Assignee | Score | Rationale |
|---|-------|---------|-------------------|-------|-----------|

*Suggestions are recommendations — team members self-select during planning.*

### 🚨 Critical Customer Bugs (exempt from capacity)
| Issue | Summary | Priority | Assignee |

### 🔧 Retro Action Items (Continuous Improvement)
| Issue | Summary | Status |

Error Handling

Error Action
Board ID not found Ask user. List available boards via acli jira board list.
No active sprint "No active sprint found. Is the team between sprints?"
No closed sprints (new team) Skip velocity. Note: "No historical data — velocity unavailable."
issueSearchStable fails Fall back to REST /rest/api/3/search.
Carryover query returns 0 "Clean sprint — no carryover. Full velocity available."

Caveats

  1. Velocity is SP-based. Teams with inconsistent SP estimation will see noisy trends. Fall back to issue count if SP coverage < 50%.
  2. Sprint fill suggestions reuse assign.md scoring. If expertise profiles aren't cached, this step adds ~5-10 API calls.
  3. Bug SP exemption. The doc says "every item needs story points or needs to be time-boxed." Bugs in the ready queue without SP are still shown but flagged.
  4. Release Pending items stay in sprint. Per team convention, Release Pending items remain in the sprint and count toward capacity.