Offshore Wind Development Structure


1. Executive overview

It provides a high-level overview of developer-side project management for bottom-fixed offshore wind farms. The objective is to give insights into how and when complex, multi-layered stakeholders are involved throughout the entire project lifecycle. In addition, it highlights the link between the project process and WTG / FOU design.


1. Project Life Cycle Overview

1.1 Stage gate structure and major activities

Phase Gate Major Activities
Concept & Origination G0 – Concept Approval Market screening, site identification, high-level wind resource review, preliminary CAPEX estimate, initial stakeholder mapping
Site Securing G1 – Site Secured Bid submission / auction participation, concession or lease agreement execution, early stakeholder engagement
Development Environmental baseline surveys, metocean deployment, grid connection application, preliminary layout, early financial model
Revenue Structuring G2 – Revenue Secured PPA / CfD negotiation and signing, tariff confirmation, revenue model finalization
Engineering (FEED) Geophysical & geotechnical surveys, WTG selection, preliminary load envelope, foundation concept design, electrical concept design, installation strategy study
Pre-FID Readiness G3 – Technical Readiness FEED completion, grid alignment confirmed, contract negotiation substantially complete, updated CAPEX & schedule
Financing G4 – Financial Close Lender due diligence, insurance placement, debt agreements executed, financial model finalized
Investment Decision G5 – FID Board approval of full CAPEX, equity commitment, risk acceptance, transition from development to execution
Execution Authorization G6 – NTP (Notice to Proceed) Contractors formally instructed to begin fabrication/manufacturing, payment milestones activated
Fabrication & Manufacturing WTG manufacturing, foundation fabrication, OSS construction, cable production
Transport & Installation Port marshalling, vessel mobilization, foundation installation, OSS installation, cable lay, turbine erection
Energization G7 – First Power Export cable energized, OSS live, first turbine connected to grid
Commissioning Mechanical completion, electrical completion, grid code testing, performance verification
Commercial Operation G8 – COD Reliability run completed, commercial operation declared
Operations Setup & Handover O&M mobilization, spare parts readiness, control room activation, final documentation & handover

1.2 Key Governance Logic

  • G2 (Revenue Secured) reduces revenue risk
  • G4 (Financial Close) reduces financing risk.
  • G5 (FID) commits capital.
  • G6 (NTP) activates execution contracts.
  • G8 (COD) marks full revenue commencement.



2. Work Breakdown Structure (Level 1 WBS) and Gantt chart

2. 1 Gantt chart - Level 1 WBS and Milestone mapping

Legend:
█ = Major activity
░ = Minor / support activity
◆ = Milestone occurs in this year

Project Duration: 6 Years
FID assumed at end of Year 3
NTP assumed early Year 4

WBS Package Y1 Y2 Y3 Y4 Y5 Y6 Key Milestones
1 Development Y1 ◆ G1 Site Secured
Y2 ◆ G2 Revenue Secured
2 Engineering Y3 ◆ FEED Complete
3 Procurement Y3 ◆ G4 Financial Close
Y3 ◆ G5 FID
4 Fabrication Y4 ◆ First Steel
5 Transport & Installation Y4 ◆ First Foundation Installed
Y5 ◆ First Turbine Installed
6 Commissioning Y5 ◆ First Power
Y6 ◆ COD
7 Operations Setup Y6 ◆ Handover to O&M



3. WBS Level 2/3

1. Development

1.1 Site Origination & Award

  • 1.1.1 Site screening & feasibility
  • 1.1.2 Auction / bid submission
  • 1.1.3 Concession / lease agreement

1.2 Environmental & Social Development

  • 1.2.1 Baseline environmental surveys
  • 1.2.2 EIA / ESIA preparation
  • 1.2.3 Fisheries & stakeholder consultation
  • 1.2.4 Permit submission

1.3 Grid & Commercial Structuring

  • 1.3.1 Grid connection application
  • 1.3.2 Preliminary grid studies
  • 1.3.3 PPA / CfD structuring
  • 1.3.4 Financial model development

1.4 Development Controls

  • 1.4.1 Development schedule
  • 1.4.2 Risk register
  • 1.4.3 Site investigation planning

2. Engineering

2.1 Site Investigations

  • 2.1.1 Geophysical survey
  • 2.1.2 Geotechnical campaign
  • 2.1.3 Metocean measurement
  • 2.1.4 UXO survey

2.2 FEED Engineering

2.3 Detailed Engineering

  • 2.3.1 WTG project-specific validation
  • 2.3.2 Foundation detailed design
  • 2.3.3 OSS detailed design
  • 2.3.4 Cable detailed design
  • 2.3.5 Protection & control design

2.4 Certification & Compliance

  • 2.4.1 Independent design review
  • 2.4.2 Grid code compliance modeling
  • 2.4.3 Class / certifier approval

3. Procurement

3.1 Contracting Strategy

  • 3.1.1 Packaging definition
  • 3.1.2 Interface matrix
  • 3.1.3 Tender documentation

3.2 Major Package Procurement

  • 3.2.1 WTG TSA
  • 3.2.2 Foundation EPCI
  • 3.2.3 OSS EPCI
  • 3.2.4 IAC EPCI
  • 3.2.5 Export Cable EPCI
  • 3.2.6 T&I contract

4. Fabrication

4.1 WTG Manufacturing

  • 4.1.1 Blade production
  • 4.1.2 Nacelle assembly
  • 4.1.3 Tower fabrication
  • 4.1.4 Factor Acceptance Test

4.2 Foundation Fabrication

  • 4.2.1 Steel procurement
  • 4.2.2 Rolling & welding
  • 4.2.3 Coating & corrosion protection
  • 4.2.4 Transition pieces
  • 4.2.5 QA/QC & inspection

4.3 OSS Fabrication

  • 4.3.1 Jacket / monopile fabrication
  • 4.3.2 Topsides build
  • 4.3.3 HV equipment installation
  • 4.3.4 Factor Acceptance Test

4.4 Cable Manufacturing

  • 4.4.1 IAC production
  • 4.4.2 Export cable production
  • 4.4.3 Factory testing

5. Transport & Installation

5.1 Port & Marshalling

  • 5.1.1 Port upgrades
  • 5.1.2 Storage & marshalling setup

5.2 Marine Strategy

  • 5.2.1 Vessel mobilization
  • 5.2.2 Marine warranty approval
  • 5.2.3 Typhoon season planning

5.3 Offshore Campaigns

  • 5.3.1 Foundation installation
  • 5.3.2 Scour protection
  • 5.3.3 OSS installation
  • 5.3.4 Cable lay & burial
  • 5.3.5 Turbine erection

6. Commissioning

  • 6.1 Mechanical Completion
  • 6.2 Electrical Completion
  • 6.3 Cold Commissioning
  • 6.4 Hot Commissioning
  • 6.5 Grid Code Testing
  • 6.6 Reliability Run
  • 6.7 Commercial Operation Date (COD)

7. Operations Setup

  • 7.1 O&M Contract Finalization
  • 7.2 Spare Parts & Warehouse Setup
  • 7.3 Control Room & SCADA Integration
  • 7.4 Service Vessel Contracts
  • 7.5 Warranty Tracking System
  • 7.6 Handover to Operations

About

High level guide for project management of offshore wind development